Completed Projects
Project Name: Robert J. Frank School
Owner: Oxnard School District
Architect: Leiden-Frost-Horowitz
Contract Amount: $1,100,000.00
Completed Date: August 1994
Project Name: Cedars Repipe
Owner: Cedars Sinai
Architect: FRBA
Contract Amount: $188,000.00
Completed Date: August 1994
Project Name: Tom Bradley International Student Center
Owner: University of California, Los Angeles
Architect: LPA
Contract Amount: $422,000.00
Completed Date: April 1998
Project Name: Sepulveda VA Hospital Chiller
Owner: Veterans Administration
Architect: Marion Rock & Associates
Contract Amount: $244,000.00
Completed Date: September 1999
Project Name: Los Angeles Trade Tech Buildings A & C Repipe
Owner: Los Angeles Community College District
Architect: Russell Holland & Associates
Contract Amount: $375,600.00
Completed Date: December 1999

Project Name: USC Surgical Center
Owner: University of Southern California
Architect: API Consultants
Contract Amount: $103,750.00
Completed Date: December 1999
Project Name: Moorpark High School Phase V(b)
Owner: Moorpark Unified School District
Architect: PSWC Group
Contract Amount: $379,974.00
Completed Date: June 2002
Project Name: See’s Chilled Water & Process Piping
Owner: See’s Candy Shops, Inc.
Architect: R.S. Herman Architects
Contract Amount: $226,798.00
Completed Date: October 2002
Project Name: Sierra Vista Jr. High School Boys & Girls Club
Owner: William S. Hart Union High School District
Architect: NTD Architects
Contract Amount: $370,317.00
Completed Date: June 2003
Project Name: Pierce College Various Plumbing Projects
Owner: Los Angeles Community College District
Architect: P.A. Breen Associates
Contract Amount: $633,840.00
Completed Date: February 2004
Project Name: Good Samaritan Hospital Water Main
Owner: Good Samaritan Hospital
Architect: NTD Architects
Contract Amount: $337,047.00
Completed Date: July 2004
Project Name: John Muir Middle School Modernization
Owner: Burbank Unified School District
Architect: Carmichael-Kemp Architects
Contract Amount: $617,577.00
Completed Date: August 2004
Project Name: Moorpark High School Gymnasium
Owner: Moorpark Unified School District
Architect: PSWC Architects
Contract Amount: $758,129.00
Completed Date: January 2005
Project Name: Hueneme High School Modernization Phase 2
Owner: Oxnard Union High School District
Architect: Flewelling & Moody
Contract Amount: $833,833.00
Completed Date: October 2005
Project Name: UCLA SEAS Cooling Tower Piping
Owner: Regents of University of California
Architect: Bechard & Associates
Contract Amount: $373,689.00
Completed Date: August 2006

Project Name: Glendale Medical Office Remodel
Owner: Chevy Chase Medical Plaza LLC
Architect: Kluger Architects
Contract Amount: $229,144.00
Completed Date: March 2007
Project Name: Saugus High School Modernization Phase 2
Owner: William S. Hart Union High School District
Architect: STV Inc.
Contract Amount: $1,360,793.00
Completed Date: April 2007
Project Name: Music Academy of the West, Hahn Hall
Owner: Music Academy of the West
Architect: Phillips Metsch Sweeney Moore
Contract Amount: $216,559.00
Completed Date: July 2008
Project Name: Los Angeles Trade Technical College Bldg. J Pool Boilers
Owner: Los Angeles Community College District
Architect: Breen Engineering
Contract Amount: $261,662.00
Completed Date: July 2008
Project Name: UCLA Sproul Hall Repairs & Refurbishment
Owner: Regents of University of California
Architect: UCLA Housing & Hospitality Services
Contract Amount: $1,623,355.00
Completed Date: September 2008
Project Name: Valley View Middle School Modernization
Owner: Simi Valley Unified School District
Architect: BFGC Architects
Contract Amount: $195,389.00
Completed Date: September 2008
Project Name: Port Hueneme Fire Station PH430 Repair
Owner: U.S. Department of the Navy
Architect: K.O.O. Construction
Contract Amount: $194,011.00
Completed Date: November 2008
Project Name: St. John’s Medical Center Building Defects Repairs Phase 01
Owner: Catholic Healthcare West dba St. John’s Regional Medical Center
Architect: RBB Architects Inc.
Contract Amount: $1,477,532.00
Completed Date: January 2009
Project Name: Los Angeles City College Child Development Center
Owner: Los Angeles Community College District
Architect: BWS
Contract Amount: $434,747.00
Completed Date: January 2009
Project Name: 707 Wilshire Lobby Renovation
Owner: Broadway 707 Wilshire Fee LLC
Architect: Simon S. Wong & Associates Inc.
Contract Amount: $314,064.00
Completed Date: June 2009
Project Name: Crowne Plaza Hotel Domestic Water Pumps
Owner: InterContinental Hotels Group
Architect: Breen Engineering Inc.
Contract Amount: $215,761.00
Completed Date: February 2009

Project Name: West Los Angeles College Pumphouse Booster Pump
Owner: Los Angeles Community College District
Architect: Breen Engineering, Inc.
Contract Amount: $132,700.00
Completed Date: September 2009
Project Name: VA Hospital Bldg. #500 Urology Clinic
Owner: U.S. Veterans Administration
Architect: Zakian Woo Architects
Contract Amount: $143,375.00
Completed Date: November 2009
Project Name: El Encanto Hotel Renovation Phase 1
Owner: Orient-Express Hotels Ltd.
Architect: Guttman & Blaevoet
Contract Amount: $734,550.00
Completed Date: January 2010
Project Name: Fort Irwin Barracks Bldg. #98
Owner: U.S. Army Corps of Engineers
Architect: ACOE
Contract Amount: $152,900.00
Completed Date: May 2010
Project Name: UCLA CHS OPAT Heat Exchanger Piping
Owner: Regents of University of California
Architect: N/A
Contract Amount: $296,135.00
Completed Date: October 2010
Project Name: VA North Hills Building #47 Ambulatory Care
Owner: U.S. Veterans Administration
Architect: PBS Engineers
Contract Amount: $239,616.00
Completed Date: October 2010
Project Name: St. John’s Medical Center CHW System
Owner: Catholic Healthcare West
Architect: Design Build
Contract Amount: $683,580.00
Completed Date: November 2010
Project Name: West Los Angeles College Water Main
Owner: Los Angeles Community College District
Architect: Breen Engineering
Contract Amount: $215,370.00
Completed Date: January 2011